LINDI: The Vice President of the United Republic of Tanzania, Hon. Deogratius Ndejembi, has directed the Prevention and Combating of Corruption Bureau (PCCB) and the Police Force to investigate the expenditure of funds for an infrastructure improvement project in Lindi Municipality. This follows reports indicating that the contractor has been paid 4.22 billion shillings, while project implementation stands at only 24%—despite 80% of the contract duration having already elapsed.
Issuing these directives today during his visit to the Lindi Region, the Vice President requested a detailed account of how payments were processed, how the funds were utilized, and the reasons why the work has not progressed at the expected pace. He further requested that the investigation report be submitted directly to him, so that he may present it to President Dr. Samia Suluhu Hassan.
He questioned why the contractor continued to receive further payments, given that the Municipal Council itself had noted a lack of financial discipline regarding the initial disbursements.
The Vice President expressed dissatisfaction with the Council’s explanation that they had sent 16 letters to the contractor concerning the sluggish progress of the work. He emphasized the necessity of taking concrete action, rather than merely exchanging correspondence, especially when public funds have already been disbursed. According to the implementation report presented during the inspection, the project—valued at 19.06 billion shillings—is being executed by Hamerkop International Limited in a joint venture (JV) with KIKIM Contractor’s Limited.
The contractor has been paid a total of 4.22 billion shillings, comprising an advance payment of 2.86 billion shillings and a payment of 1.36 billion shillings processed via payment certificate number two.
The project contract was signed on June 25, 2025, in Dodoma, with work officially commencing on November 7, 2025. The project is scheduled for completion by February 5, 2027. According to the report, implementation was expected to have reached 80 percent by this stage; therefore, the 24 percent completion rate achieved represents a shortfall of 56 percentage points.
The project, which is being implemented under the TACTIC program, encompasses the Matopeni Main Market, 5.3 kilometers of roads, the Mitwero Bus Terminal, and a project coordination office. It is funded by the World Bank through the Government under the President’s Office – Regional Administration and Local Government (PO-RALG), with technical supervision provided by Inter-Consult Limited in collaboration with Tanzo Vision Engineering Limited. Delays in construction prompted the Minister responsible for TAMISEMI, Professor Riziki Shemdoe, to conduct an inspection on September 14, 2026. He directed the contractor to engage capable subcontractors and ordered the formation of a special monitoring team. The team determined that the primary contractor lacked the capacity to complete the project within the scheduled timeframe. It recommended that the contractor retain responsibility for the construction of the market, while three other components of the project be assigned to subcontractors.
According to reports, a subcontractor for the road works has been secured, while the search for contractors for the bus terminal and office facilities is still ongoing.
Issued by
The Office of the Vice President
November 14, 2026
Lindi.